Cardinal Oaks Park - Measure G Projects

The Measure G projects are coming soon to Cardinal Oaks Park!  The following are included in this phase:

  • Demo and grading of existing play area.
  • New playground structure and surface.
  • ADA Work including exterior routes of travel, ramps and drinking fountains.
  • Added pedestrian lighting.
  • New parking lot at south-end of the park.

Project Completion Estimated Timeline: Fall 2026

Timeline: 

  • Current Progress (April 2026): Contract approved by the Sacramento County Board of Supervisors. CRPD is working with Xeela Engineering LLC on contract and insurance submissions. Construction is likely to begin in late May 2026 and run through late September 2026.
  • March 2026: Re-released RFP for Landscape Contracting Services. Intent to award the contract to the lowest responsible bidder, Xeela Engineering LLC was approved by the Advisory Board on 3/19/25 (Action 2). Due to the amount, the contract was sent to the Sacramento County Board of Supervisors for approval.
  • December 2025: Released RFP for Landscape Contracting Services.
  • November 2025 - Received permits from the County of Sacramento
  • November 2024 - Plans submitted to County of Sacramento for permits. Awaiting permits.
  • October 17, 2024 - Design Presentation at the Advisory Board Meeting - Presentation
  • October 1, 2024 - Community Meeting - Community Meeting Presentation
  • September - October 2024 - Community Online Survey

 