Cardinal Oaks Park - Measure G Projects
The Measure G projects are coming soon to Cardinal Oaks Park! The following are included in this phase:
- Demo and grading of existing play area.
- New playground structure and surface.
- ADA Work including exterior pathways, ramps and drinking fountain.
- Added pedestrian lighting.
- New parking lot at south-end of the park.
Project Completion Estimated Timeline: End of 2026
Timeline:
- Current Progress (November 2026): Parking lot asphalt installation to occur in early/middle of November. Remaining irrigation and grading at the parking lot area is in progress.
- October 2026: Rubber Surfacing installed at the beginning of the month, with a playground inspection scheduled for the end of October. Installation of the light poles is scheduled for the last week in October. Parking lot curb installation and frontage work completed.
- September 2026: Playground installation is underway! The construction team is currently completing all the concrete flatwork. The parking lot concrete and flatwork walkways are targeted for mid-September, with the pour-in-place rubber surfacing installation toward the end of the month.
- August 2026: Significant activity is underway! Aggregate base placement on the parking lot has begun, dirt offhaul is complete, and the playground installer is on site and expected to finish late August/early September. New light poles are expected to arrive in late October.
- July 2026: Irrigation installation is ongoing, and metal fence installation is underway. Preparation for dirt removal is in progress.
- June 2026: The contractor has begun to install irrigation and drainage for the new design. Formwork installation will begin soon.
- May 2026: Construction begins on 5/11/26. Temporary fencing will be put in place with a partial park closure. Ribbon Cutting event on 5/27/26 at 9am. Please plan for a complete park closure from 5/28/26 to the beginning of August. Project completion is scheduled for the end of October 2026.
- April 2026: Contract approved by the Sacramento County Board of Supervisors. CRPD is working with Xeela Engineering LLC on contract and insurance submissions. Construction is likely to begin in late May 2026 and run through late September 2026.
- March 2026: Re-released RFP for Landscape Contracting Services. Intent to award the contract to the lowest responsible bidder, Xeela Engineering LLC was approved by the Advisory Board on 3/19/25 (Action 2). Due to the amount, the contract was sent to the Sacramento County Board of Supervisors for approval.
- December 2025: Released RFP for Landscape Contracting Services.
- November 2025 - Received permits from the County of Sacramento
- November 2024 - Plans submitted to County of Sacramento for permits. Awaiting permits.
- October 17, 2024 - Design Presentation at the Advisory Board Meeting - Presentation
- October 1, 2024 - Community Meeting - Community Meeting Presentation
- September - October 2024 - Community Online Survey

Cardinal Oaks Park - Plan Overview

Approved concept plan

Playground replacement rendering





















































































































































