Glancy Oaks Park - Measure G Projects
The Measure G projects have started at Glancy Oaks Park! The following are included in this phase:
- Demo and grading of existing play area.
- New playground structure and surface.
- ADA Work including accessible, paved park entry at southwest corner of the park, exterior routes of travel, ramps and drinking fountains.
Timeline:
- Current Progress (August 2025): Construction is underway on new accessible pathways, helping make the park more inclusive and easier to navigate for all.
- July 29, 2025 - Groundbreaking Event
- June 2025 - Awarded and excuted construction contract
- May 16, 2025 - Advisory Board Meeting - Action 4 - Approve Updated Total Project Budget and Accept the Lowest Responsible Bid from Saenz Landscape Construction for Glancy Oaks Park Improvement Project
- November 21, 2024 - Design Presentation at the Advisory Board Meeting - Meeting Presentation
- September 19, 2024 - Design Presentation at the Advisory Board Meeting - Meeting Presentation
- September 17, 2024 - Community Meeting - Meeting Presentation
- August - September 2024 - Community Online Survey