O'Donnell Heritage Park - Measure G Projects
The Measure G projects are coming soon to O'Donnell Heritage Park! The following are included in this upcoming series II:
- Addition of an accessible concrete walkway around the park.
- Site furnishings and accessible park accessories.
Estimated Completion Date: August 2026
Timeline:
- Current Progress (June 2026): Construction on the walkways continues with more walkways being prepared and concrete being poured. Landscape work will begin around 6/15.
- May 2026: Construction underway with preparation of walkways for concrete.
- April 2026: CRPD is working with Lister Construction on contract and insurance submissions. Construction is scheduled to start in May 2026 and run through August 2026.
- March 2026: Intent to award the contract to the lowest responsible bidder, Lister Construction, was approved by the Advisory Board on 3/19/25 (Action 4).
- February (2026): RFP for Landscape Contracting released.
- January (2026): O'Donnell Heritage Park Conceptual Design presented by MTW Group at the CRPD Advisory Board Meeting on 1/15/26 and approved.